Meeting individual requirements

High performance, full automation, and not much space. Impossible? No!
The competence and innovation team at IMA Schelling proved this once again at the spanish furniture manufacturer Gamadecor.

PLAN, DEVELOP, SPEAK WITH THE CUSTOMER


Project engineers from IMA Schelling had a detailed discussion and exchange of ideas with the customer, and looked at the production conditions at the Villareal site. They planned, developed, and looked for creative concepts. And they finally found a solution that met all the requirements.

At the heart of the solution is the batch size 1 cut-to-size and machining system Performance.cut. This is fitted with milling units which can not only be used to cut boards to size, but they can also perform additional tasks such as grooving and drilling, as well as rabbeting and making diagonal cuts. Equipped with two main spindles, the system produces an above-average cutting performance of 1750 components per shift, that allows the total output called for by Gamadecor to be achieved with just one machine. "Which saves space, of course," stresses Schumacher. It also reduces the cost of investments in a suction system and operating personnel. 

GAMADECOR


Villareal-based Gamadecor is a renowned manufacturer of extremely high-quality kitchen and bathroom furniture that is also much in demand beyond Spanish borders. Which is why an increase in capacity was on the agenda for the company. The challenge they faced, however, was limited production hall space, and the high output and quality requirements of the production department. The company took their problem to plant experts IMA Schelling, with whom Gamadecor has enjoyed a close working relationship for almost 15 years. 

"This was actually a real challenge," says Ralf Schumacher, Sales Area Manager at IMA Schelling. "They wanted a fully interlinked, fully-automated batch size 1 unit for producing front panels and hollow ware, where parts or remnants could be manually added or removed at different positions." The system also had to be connected to the existing assembly line, and should achieve a capacity of at least 1300 to 1400 components per shift – and all that to fit in a space that could not exactly be described as generous.

FOUR INFEED AND DISCHARGE POSITIONS


Attached to the Performance.cut is a Combima combined automatic finished part and edge processing machine, where the boards are edge-banded by applying glue or using a laser, as required. A vertical parts buffer is interposed to even out differences between the output capacities of the two systems.

Furniture manufacturer Gamadecor has been using custom plants from IMA Schelling for their production for many years, and is highly satisfied.

The new plant includes:

  • The Performance.cut cut-to-size system
    • With two main spindles
  • The Combima edge-banding system
    • With parallel milling station
    • Servo grooving station
    • Edge banding unit with upstream glue application for "changing on the fly" between glue and laser edge-banding
    • our additional servo milling units for profile milling MDF front panels
  • Handling components
    • Two sorting robots
    • Turning stations for the assembly line
    • Handling with pairing
  • IPC.Net system control
    • Planning
    • Optimization
    • Flow of materials
    • Evaluations

IMA Schelling equipped the entire plant with a total of four feeding or discharging options. Left-over parts can be removed after the Performance.cut, cut to size on an existing saw, and then fed back in. This is also possible after the edge-banding process and before sorting. To save even more space, IMA Schelling experts configured transport units in various places on two levels, one above the other horizontally.

This is the most efficient way to organize the flow of materials, and was the best way to integrate existing Gamadecor processes. The entire plant is controlled by the IPC.Net system control from IMA Schelling.

For customers, this has the major advantage that everything comes from a single source – without any interface problems.

TWO PASSES INSTEAD OF FOUR


IMA Schelling also found a creative solution to another challenge. Gamadecor wants to profile mill MDF front panels as well as particle board components, so it was necessary to have additional machining units. To save time when machining particle boards by way of compensation, the engineers developed a special solution for the particle board components such as shelves that are only given a glued edge on the long side. "We have incorporated a parallel milling station for these parts," explains Ralf Schuhmacher. Here the shelves, etc., are produced in only two edge processing passes, instead of the usual four passes. 

An original concept was also required at the end of the machining process, as Gamadecor needs the workpieces to be in an upright position for the subsequent assembly line. "We integrated a dynamic workpiece turner in front of the sorting unit, and a workpiece upending station after it," explains Schumacher. For the actual sorting, IMA Schelling developed two, highly-efficient sorting cells, each with a Robot.Sort robot and four sorting shelves, to take the maximum number of cut-to-size parts from a single shift. 


 

CUSTOMER REQUIREMENTS TAKE TOP PRIORITY


"We are only satisfied once the customer is satisfied. Their individual requirements set the benchmark for our development and project management work," stresses Simon Waterbär, Director of Sales at IMA Schelling.

"For Gamadecor, we configured a custom complete solution from our high-tech systems, with some truly original production processes." When developing customer-specific production solutions like this, experienced engineers work together in the project management team with experts in material flow simulation, system control, robotics, and cut-to-size and performance calculations, as well as plant design.

GLOSSARY


 

1 area storage vs 12

2 cutting system Performance.one

3 labeling system

4 buffer system with 14 floors

5 feeding and discharging station for hand remnants

6 pair formation

7 fully automated edgebanding system type Combima Systems with pair handling

8 hedgehog buffer for discharging fronts

9 buffer system with 20 floors

10 workpiece turning device, infeed and outfeed station for back panels

11 sorting cell Robot.sort v with 4 shelves for package handling

12 sorting cell Robot.sort v with 4 shelves for package handling

13 workpiece erection for transfer of carcase material to the assembly line

SOLUTION - THE FUTURE MAGAZINE


back to the magazine